Kit Prices and Lead Times

RV Kit Prices

Please refer to the individual kit-order pages for the latest kit and upgrade prices.

Kit Lead Times

Below are the estimated lead times for Van’s RV kits. These lead times are updated regularly to reflect the approximate timeframe in which we expect to have each kit available to be crated for a customer.

  1. We cannot always control the availability of certain materials and parts. While we work diligently to gather lead times for third-party components, we rely on timely delivery of those parts when we are estimating lead times for your kits that include those components.
  2. The kit(s) you order may be available and delivered sooner than the published lead time. Please plan and be ready to take possession of your order as soon as it is ready to deliver, because we cannot store completed kits once they are ready to ship even if they are ready earlier than was estimated. Customer-initiated delays to the acceptance of ready-to-deliver kit(s) may result in the original price being updated to the price effective on the new delivery date, and/or may require us to deliver your kit to another customer and reassign your order to a future production batch.
  3. We ship individual kits as soon as they are produced and ready to ship. We are unable to make commitments to hold completed kits to combine with another kit(s) for shipping. Please be prepared and understand that each sub-kit will need to ship separately. If our team happens to be able to ship multiple kits together due to a “happy” schedule alignment we will do so, of course, but we cannot entertain requests to hold and combine kits in a single shipment.

Quick Build Fuselage and Wing customers may experience variability in projected lead times due to delays in overseas shipping of parts to and from our QB contract assembly facilities. Lead times may also vary depending on our current factory stock and/or stock of available parts at the assembly facilities. Since containers are shipped to the quick-build facilities approximately every 2-3 months, it is possible that QuickBuild kit orders placed only days apart could have significantly different lead/completion times.

Estimated lead times as of: 1/2/26
RV-7/7A RV-8/8A RV-9/9A RV-10
Empennage/Tail 4 Weeks 4 Weeks 4 Weeks 4 Weeks
Wing 12 Weeks 12 Weeks 8 Weeks 8 Weeks
Fuselage 22 Weeks 16 Weeks 22 Weeks 10 Weeks
Finishing 22 Weeks 16 Weeks 22 Weeks 12 Weeks
QuickBuild Wing 26 Weeks 39 Weeks 39 Weeks 26 Weeks
QuickBuild Fuselage 39 Weeks 26 Weeks 39 Weeks– 26 Weeks
RV-12 RV-14/14A RV-15
Empennage/Tail 4 Weeks 4 Weeks TBD
Wing 16 Weeks 8 Weeks 20 Weeks
Fuselage 16 Weeks 10 Weeks TBD
Finishing 22 Weeks 12 Weeks TBD
Avionics 30 Weeks
Powerplant 21 Weeks
QuickBuild Wing NA 26 Weeks NA
QuickBuild Fuselage NA 26 Weeks NA

3rd-Party Manufactured Items – Lead Times:

Lead times for all engines and propellers are estimated. These products are made-to-order. Each manufacturer determines the schedule and lead times for their products. Van’s is not responsible for changes to third-party manufacturer lead times.

Hartzell Propellers: 8 weeks
4-Cylinder Lycoming Experimental Engines:  18 months (depending on model/options)
6-Cylinder Lycoming Experimental Engines:  18 months (depending on model/options)
Lycoming Thunderbolt Experimental Engines (all):  14 months (depending on model/options)